Locatie Open Oproep 1305 © Jan Kempenaers

Locatie Open Oproep 1305 © Jan Kempenaers

Locatie Open Oproep 1305 © Jan Kempenaers

Locatie Open Oproep 1305 © Jan Kempenaers

Locatie Open Oproep 1305 © Jan Kempenaers

Locatie Open Oproep 1305 © Jan Kempenaers

Locatie Open Oproep 1305 © Jan Kempenaers

Locatie Open Oproep 1305 © Jan Kempenaers

Locatie Open Oproep 1305 © Jan Kempenaers

Locatie Open Oproep 1305 © Jan Kempenaers

Locatie Open Oproep 1305 © Jan Kempenaers

Locatie Open Oproep 1305 © Jan Kempenaers

Luchtfoto © GDI-Vlaanderen

Luchtfoto © GDI-Vlaanderen

Project description

Oudenaarde is an East Flanders town second only to Ghent in its artistic wealth. It arose on the banks of the River Scheldt, which has always played an important part in the town's history. The straightening of the river in 1970 created a harsh spatial rift in the town. Numerous buildings were demolished. The old arm of theScheldtwas filled in and the historical town was cut off from the right bank of the river, which includes Pamele.
Oudenaardetown council is in the midst of reorganisingthis old arm of the river as a green lung that runs through the whole area and of reorganisingthe present bank of the river as a transitional zone between the urban and rural areas, which enables the river once again to be experienced as part of the urban fabric. The main means of access to the area is along the old route of the river, which isconverted into an urban boulevard with green verges full of trees and a generous public space.
The area contains several zones, each with its own identity. In the filled-in river zone there are park sections with a lateral pedestrian route. The following functions have also been included here: green car parking, a multipurpose square, a short cut to the market square, a playground, a green recreational park with vegetation, etc.
This assignment also includes the generation of an idea for the public space along the Scheldekaaiand Jan ZonderVreeslaan-Achterburgas far as the entrance to the beguinage.
The client expects the designer to provide an integrated plan that incorporates roads, towpath, parking and promenade. Part of the quayside (adjacent to the green zone) may be excavated to a level of 1.25 m above the waterline.

Oudenaarde OO1305

Complete study assignment to draw up a masterplan for the publicspace at De Ham in Oudenaarde.

Project status
Selected agencies
  • Atelier JPLX bvba
  • Arcadis Belgium nv, Brut Architectuur & Stedenbouw
  • HOSPER NL BV
  • Paul Deroose
  • Puls_net cvba
Location

De Ham 12 (ter hoogte van), 9700 Oudenaarde
Centrum Oudenaarde, De Ham

Timing project
  • Selection: 16 May 2007
  • Toewijzen opdracht aan de ontwerpers: 6 Aug 2007
  • First briefing: 29 Aug 2007
  • Submission: 12 Nov 2007
  • Jury: 21 Nov 2007
  • Award: 21 Nov 2007
  • Realization: 21 Dec 2007
Client

Stadsbestuur Oudenaarde

contact Client

Vanquickenborne Luc

Procedure

prijsvraag voor ontwerpen met gunning via onderhandelingsprocedure zonder bekendmaking.

External jury member

Pieter Jacobs

Awards designers

€7.000 /laureaat

Downloads

projectdefinitie